More work areas have been opened for other trades such as plumbing, exterior walls, mechanical, and electrical. During February, you should see more concrete walls being erected and beginning in late February, the brick work on the south stairwell tower should begin. Also in February, all stairways should be roughed in.
Building E is also on track. Structural steel and metal decking is almost complete. While detailing of the steel structure continues, as with building A, additional work areas for other trades are opening up. |