The roofing material is on and window placement is in progress. The buildings will be closed up and the HAVC systems will be turned on in the very near future. As soon as the buildings are weatherproofed, the interior finishing items, which are sensitive to humidity, will be installed.
One item which has been delayed numerous times is the tapping onto the county water lines. Since the tapping will occur on the road right-of-way, permits are required. After the tapping, the charging of the fire sprinkler system will take place. This must occur before the wall and ceiling materials are installed so that leaks (if any) can be addressed.
|